Baltic Data Centre & Power Tracker
Compare selected projects in Estonia, Latvia and Lithuania. Grid applications, reservations, facility capacity and IT load are tracked separately.
| Project | Status | Power update |
|---|---|---|
| Greenergy Hüüru expansion | Under construction | Grid application filed; 22 MW hall planned |
| Tet DC7 | Phase 1 opened | Phase 1 opened; electrical MW not disclosed |
| Kruonis DC | Planning | Up to 200 MW grid reservation; energisation unconfirmed |
| Telia Raisteniškės | Under construction | 2 MW initial facility design |
How capacity is classified
- Requested grid capacity
- Capacity sought from a network operator; not evidence of approval.
- Secured connection capacity
- Capacity the network operator confirms as reserved or contracted. A conditional reservation is not an energised connection.
- Facility capacity
- Power reported for a site, phase or hall. A design figure or expansion target is not operating capacity.
- IT load
- Power explicitly attributed to computing equipment, excluding building overhead.
These figures are not additive. A value marked not disclosed is missing from the sources checked, not zero. The tracker covers selected projects, not a complete market inventory.