Greenergy Hüüru expansion
An expansion at the existing Greenergy campus. This record covers the new development, not the operating capacity of the original site.
- Location
- Hüüru, Harju County, Estonia
- Operator or developer
- MCF Group Estonia (Greenergy Data Centers)
- Development status
- Under construction [1]
- Record checked
Power and connections
| Capacity type | Disclosed power and scope |
|---|---|
| Requested grid capacity |
MW not disclosed
MCF reported applying to Elering for more grid capacity. Its release did not specify the MW in the application. [1]
|
| Secured connection capacity | Not disclosed |
| Facility capacity |
22 MW
First Nebius hall. Operator-announced deployment figure; not an independently specified IT load. [2]
About 200 MW
Potential future campus capacity contingent on a larger grid connection. Not the requested or secured grid figure. [1]
|
| IT load | Not disclosed |
Investment activity
Approximately €100 million
Operator-announced expansion investment, not confirmed expenditure. [1]
Project milestones
- MCF announced the expansion, said preparatory work had begun and disclosed its application to Elering. [1]
- Greenergy announced Nebius as the customer for its first 22 MW hall. [2]
- Operator target for the first Nebius phase to go live; opening not confirmed in the cited releases. [2]